Sherwin-Williams

Client: Sherwin Williams

Site: Tournes, France

Application: Acrylate treatment system; 99.95% removal efficiency of; methyl and butyl; methacrylate plus carrier

Equipment: 304SS packet tower scrubber, 304SS carbon filter, 304SS fan 1,000 m3/hr, 304SS discharge stack, Duty/standby 316SS mag, drive recirculation pump, Chemical dosing system, Generally in accordance with, PD5500 CAT 3 & SEP and Control system

Year delivered: 202

ERG delivered the Sherwin-Williams project for Sherwin Williams at Tournes, France in 2023. The case study identifies the application as Acrylate treatment system; 99.95% removal efficiency of; methyl and butyl; methacrylate plus carrier. The project formed part of ERG’s work in engineered air-pollution control and process-gas treatment, with the supplied package tailored to the operating context recorded on the original case sheet.

Case Studies

Industrial gas cleaning/Thermal systems

System Maintenance

Odour control

Plastic-GRP Fabrication