Client: WABAG
Application: Treatment of H2S; OCU-1 capacity 47,500m*/hr; OCU-2 capacity 40,200m*/hr; OCU-3 capacity 182,000m*/hr
Year delivered: 2009
ERG delivered the DSSTW-WABAG project for WABAG in 2009. The case study identifies the application as Treatment of H2S; OCU-1 capacity 47,500m*/hr; OCU-2 capacity 40,200m*/hr; OCU-3 capacity 182,000m*/hr. The project formed part of ERG’s work in engineered air-pollution control and process-gas treatment, with the supplied package tailored to the operating context recorded on the original case sheet.