Client: GSK
Site: Montrose, Scotland
Application: Process scrubber treating bromination; area process vents — batch scrubbing; Up to 1,300m*/hr gas flow; 1,600 g/m? Br,, 1,100 g/m* HCl, >99.999%
Equipment: ECTFE lined GRP scrubber and sump, BS, EN 13121 and, PED:SEP, ETFE lined magdrive pumps, PFA lined pipework & valves, 316 SS fan, Instrumentation and LIBs for site, connection to DCS, Skid mounted with integral access and ATEX: EX 11 2G IB T4
Year delivered: 2013
ERG delivered the GSK project for GSK at Montrose, Scotland in 2013. The case study identifies the application as Process scrubber treating bromination; area process vents — batch scrubbing; Up to 1,300m*/hr gas flow; 1,600 g/m? Br,, 1,100 g/m* HCl, >99.999%. The project formed part of ERG’s work in engineered air-pollution control and process-gas treatment, with the supplied package tailored to the operating context recorded on the original case sheet.