Chemical Scrubber Refurbishment at Broomfield Bank Sewage Treatment Works, Dover
Project Overview
ERG Air Pollution Control replaced a failing odour control system at Southern Water’s Broomfield Bank Sewage Treatment Works in Dover. The project was delivered in 2022 at a live underground facility where the replacement scrubbers had to fit through the existing plant room doorway and connect to the original ductwork.
ERG acted as Principal Designer and Contractor. Its scope covered removing the old system and designing, manufacturing, installing and commissioning the new odour control unit (OCU). The replacement used two parallel chemical scrubbers for a stated airflow of 76,500 m³/h, with new recirculation pumps and pipework, ductwork modifications and reuse of serviceable assets.
The new scrubbers were smaller than the original vessels. The project sheet reports that they achieved the same treatment standard of below 250 ppb hydrogen sulphide (H₂S).
The Challenge – Replacing a Failing System at a Live Underground Works
The original odour control unit had become inefficient. Several scrubber vessels and a pump had mechanically failed, and chemical leaks had restricted access to the area for Southern Water staff and contractors. The refurbishment therefore had to address both the condition of the treatment equipment and the practical difficulties of removing and replacing it underground.
The doorway into the OCU room constrained the size of equipment that could be brought in. At the same time, the replacement needed to connect to the original ductwork. The design had to account for the route into the room, the available space once inside and the position of the existing connections.
Removing the original equipment also needed to be coordinated with work at a live treatment site. The project sheet records that the original OCU was bypassed and three original scrubber vessels were cut up as part of the replacement works.
ERG’s Solution – Sectional Scrubbers for Restricted Access
ERG manufactured the two replacement scrubbers in sections sized to suit the doorway into the underground OCU room. This allowed the vessel sections to be brought into the room for assembly, so the dimensions of the doorway did not dictate the size of the finished vessels.
The new scrubbers were designed to tie in with the original ductwork connections. Ductwork modifications and reuse of serviceable assets formed part of the refurbishment. This approach allowed the design to focus on replacing the failed treatment equipment while making use of infrastructure that was suitable for the revised arrangement.
The two scrubbers were arranged in parallel, creating separate paths for the extracted air. In a parallel system, the resistance through each path affects how the flow divides. The vessel connections and ductwork therefore need to be considered together when designing for the overall airflow.
Chemical Scrubbing for Hydrogen Sulphide Odour Control
Chemical scrubbing treats suitable gaseous contaminants by bringing extracted air into contact with a scrubbing liquid. Hydrogen sulphide can transfer into the liquid, where suitable chemical conditions help retain or convert it. The process depends on effective contact between the gas and liquid and on maintaining the condition of the circulating liquor.
At Broomfield Bank, the replacement scope included recirculation pumps and pipework alongside the scrubber vessels. The liquid circuit is central to the treatment duty because it delivers scrubbing liquor to the vessel and returns it for recirculation. Its layout also affects how operators can inspect and service the pumps and connections in a restricted plant room.
Installation and Commissioning
ERG’s role covered the transition from the original plant to the commissioned replacement. Sectional manufacture addressed how the equipment would reach the room. The design of the vessel connections and ductwork modifications addressed how it would fit into the existing system once there.
The project sheet reports that the two smaller replacement scrubbers achieved the same treatment standard as the original vessels, below 250 ppb H₂S. This is the treatment standard recorded for the project.
Project Technical Specifications
Parameter | Project details |
Client | Southern Water |
Site | Broomfield Bank Sewage Treatment Works, Dover |
Application | Refurbishment of a failing chemical scrubber system |
Site conditions | Live underground sewage treatment works with restricted access to the OCU room |
Replacement equipment | Two parallel chemical scrubbers |
Stated system airflow | 76,500 m³/h |
Reported treatment standard | Below 250 ppb H₂S |
Vessel construction approach | Manufactured in sections to suit the OCU room doorway |
Liquid handling | New recirculation pumps and pipework |
Integration | Ductwork modifications, tie-in to original connections and reuse of serviceable assets |
ERG role | Principal Designer and Contractor for removal, design, manufacture, installation and commissioning |
Year delivered | 2022 |
Engineering Benefits
- Replacement through restricted access. Sectional manufacture allowed the new vessels to be brought through the existing doorway for assembly inside the underground room.
- Integration with existing infrastructure. The replacement was designed around the original ductwork connections and reused serviceable assets.
- Same treatment standard in smaller vessels. The case sheet reports that the replacement met the existing standard of below 250 ppb H₂S.
- One scope from removal to commissioning. ERG’s role covered the changeover from the failed equipment to the commissioned replacement.
ERG’s Expertise in Scrubber Refurbishment
Broomfield Bank illustrates how access constraints, existing connections and treatment requirements can shape a scrubber replacement. ERG can assess which assets are suitable for reuse and design replacement equipment around the route into the plant room, the space available and the required airflow.
Contact ERG Air Pollution Control to discuss chemical scrubber refurbishment or replacement at a live wastewater treatment facility.
