Client: Doosan Babcock for GSK
Site: Montrose
Application: LEV and reactor vent; scrubbing
Equipment: 3-stage scrubber package, 1 316 SS packed tower, 2 ECTFE/GRP packed, tower, 3 316 SS carbon filter, Fans, pumps, pipework and ductwork, access structure
Year delivered: 2016; PROJECT; DETAILS
ERG delivered the Doosan GSK project for Doosan Babcock for GSK at Montrose in 2016; PROJECT; DETAILS. The case study identifies the application as LEV and reactor vent; scrubbing. The project formed part of ERG’s work in engineered air-pollution control and process-gas treatment, with the supplied package tailored to the operating context recorded on the original case sheet.